Sample HTML report

Assay Gateway Pre-Review Report

Confidential sample

Gateway evidence readiness report

A document-based pre-review of the evidence pack, designed to show the issues most likely to put a Green outcome at risk before the official review team arrives.

Readiness signal

Amber

Green is achievable, but six evidence gaps need owner action before review week.

Programme

North Coast Service Modernisation

Review point

Gate 3, Investment decision

Criteria set

Australian Government RMG 106

Prepared by

Assay, Leva Solutions Pty Ltd

Executive summary

What the pack says right now.

The pack is directionally strong on strategic need and governance, but it is not yet clean enough to walk into review week with confidence. The main issue is consistency: cost, risk, schedule, and benefits evidence tell different versions of the programme.

Assay found three critical findings and six essential findings. The fastest path to a Green-ready pack is to reconcile the baseline dates, link benefits to funded milestones, and close the risk treatment evidence gaps before document freeze.

Official review alignment

Similar structure. Different authority.

RMG 106 describes final assurance reports as including delivery confidence, findings, recommendations, conclusions, background, purpose, scope, approach, logistics, documents reviewed, stakeholders interviewed, and progress against previous recommendations.

This sample mirrors the document-facing parts of that structure. It does not include interviews, reviewer judgement, signed assurance conclusions, or an official Delivery Confidence Assessment.

Evidence scorecard

Key focus area readiness

Status reflects evidence quality in the supplied documents, not the final review team rating.

Red

2

Major contradictions likely to draw reviewer challenge.

Amber

1

Evidence exists but needs better linkage or owner action.

Green

2

Material is clear enough to support review discussion.

Focus area Evidence status Reviewer question likely to follow
Business case and strategic fit Green Can the team show current policy alignment and benefits ownership?
Schedule and delivery controls Red Which baseline is authoritative, and who approved the change?
Risk and issue management Red Are critical risks funded, owned, and reflected in the business case?
Benefits realisation Amber Do benefits have measures, dates, and accountable owners?
Governance and assurance Green Are decisions captured and escalations visible?

Key findings and recommendations

Priority findings to fix first.

Critical, do now

Gate 3, KFA 4.2

Schedule control

The approved schedule baseline conflicts with the investment decision pack.

The business case assumes contract award in September, while the integrated master schedule and procurement plan show November. The risk register still models the September date, which understates exposure.

Evidence: Business Case p.42-45, Schedule p.18-22, Risk Register p.7-9

Suggested action

Confirm the authoritative baseline, update dependent documents, and minute the decision before document freeze.

Critical, do now

Gate 3, KFA 2.1

Benefits realisation

Benefits are asserted, but not tied to funded milestones.

The benefits plan names four public outcomes, but only one is linked to a funded deliverable in the forward work plan. Reviewers are likely to ask how benefits will be measured and reported.

Evidence: Benefits Plan p.11-16, Delivery Plan p.30-36, Budget Model p.6

Suggested action

Add a benefits traceability table showing owner, measure, baseline, target, delivery milestone, and reporting forum.

Essential, do by

Gate 3, KFA 5.3

Stakeholder readiness

Stakeholder evidence is current for delivery partners, but weak for central agencies.

The engagement plan lists Treasury and Finance as critical stakeholders. The latest evidence pack includes no engagement record for either group in the past 90 days.

Evidence: Engagement Plan p.8-10, Communications Log p.41-49

Suggested action

Update the stakeholder log and include planned review-week briefings for central agency stakeholders.

Action plan

Recommended owner actions.

Priority Action Owner Target
Critical Confirm the authoritative baseline, update dependent documents, and minute the decision before document freeze. Programme Director Before pack freeze
Critical Add a benefits traceability table showing owner, measure, baseline, target, delivery milestone, and reporting forum. Benefits Lead Within 5 business days
Essential Update the stakeholder log and include planned review-week briefings for central agency stakeholders. PMO Lead Before planning meeting

Background

Programme context.

The programme seeks investment approval for a staged service modernisation across regional operating sites. The stated objectives are improved service resilience, reduced operating cost, and better customer access.

Purpose, scope and approach

What Assay checked.

Assay checked the supplied documents against the selected Gate 3 criteria, identified missing evidence, compared claims across documents, and prioritised fixable issues. No interviews were conducted.

Documents reviewed

Evidence pack coverage.

Business Case v4.2

86 pages, received 22 Apr 2026

Integrated Master Schedule

42 pages, received 22 Apr 2026

Risk Register

19 pages, received 22 Apr 2026

Benefits Realisation Plan

28 pages, received 22 Apr 2026

Governance Pack

64 pages, received 23 Apr 2026

Stakeholder Engagement Plan

31 pages, received 23 Apr 2026

Previous recommendations

Action taken evidence.

Previous action Evidence found Assay view
Strengthen benefits ownership. Benefits owners named, but measures and funded milestones are incomplete. Partially addressed
Clarify governance escalation path. Board terms of reference and escalation map are aligned. Addressed

Scope limits

This is a pre-review document check, not an assurance opinion.

Assay does not replace the independent review team, conduct stakeholder interviews, sign the official report, assign a Delivery Confidence Assessment, or predict the final Gateway outcome. It shows where the supplied documents are likely to be challenged.